PROJECT DESCRIPTION / ENGINEERING SCOPE OF WORK:
The project involves a hydrologic evaluation for
the hydrologic reconnection of the F2 and F3 Lake Francis mosquito control
impoundments with the Indian River Lagoon. Using the survey data for
impoundments F2 and F3 provided by SES, a limited evaluation of existing
impoundment hydrologic exchange capacity was conducted based on impoundment
geometry and a simplified representation of tidal dynamics. This hydrologic
evaluation was achieved utilizing mathematical calculations, field
observations and HYDROLOGIC & HYDRAULIC modeling
using icpr.
|