INDIAN TRACE COMMONS
CLIENTS:
RM INVESTMENTS, LLC
LM DEVELOPMENT GROUP
LOCATION:
SUNRISE, FLORIDA
ESTIMATED
CONSTRUCTION COST:
$4,000,000
|
|
|
PROJECT DESCRIPTION / ENGINEERING SCOPE OF WORK:
Scope of work included adding roof runoff
drainage connections to existing catch basins for a 5 story office building
located within a larger shopping center. The existing shopping center's permits
with the City of Sunrise, CBWCD and South Florida Water Management were updated.
City of Sunrise required a permit modification of the existing permit. Central
Broward Water Control District did not require a complete permit approval
through the Board to add roof runoff connections, only a review by the District
Manager. South Florida Water Management allowed for a No Notice General Permit
and also did not require Board approval. A fire protection connection longer
than 50 feet did require us to permit the fire line through Broward County HRS.
Construction expected to commence in November 2007.
|